The main contractor on the $11 billion Western Sydney Airport metro project has halted payments to subcontractors, citing delayed progress payments from the New South Wales (NSW) government. Webuild, part of the Parklife Metro consortium overseeing the project, informed subcontractors this week that it could not settle approved invoices for October work due to Sydney Metro’s alleged failure to release funds.

This development intensifies a protracted dispute between Parklife Metro and the NSW Labor government. Last Friday, the government rejected Parklife’s $2 billion claim for additional funding, effectively ending negotiations. The payment standstill has raised alarm within the construction industry, with subcontractors facing financial uncertainty ahead of the Christmas break.

An industry veteran remarked that non-payment to subcontractors on a tier-one government infrastructure project is virtually unprecedented. Sydney Metro, however, denied withholding progress payments. A spokesperson stated that progress payments have not been withheld and urged Parklife Metro and Webuild to uphold their obligations to subcontractors.

Webuild declined to comment on the matter. Meanwhile, the CFMEU NSW executive officer Karma Lord questioned Webuild’s justification for non-payment, pointing out that the global contractor reported nearly $500 million in profits last year and amassed $24 billion in revenue. “A global construction giant ... can’t possibly claim cash-flow problems,” Lord said.

An anonymous subcontractor noted that continuing work would be difficult beyond a few weeks without payment, particularly with Christmas shutdowns looming. They warned that early stops by some subcontractors, such as traffic controllers, could halt the entire project due to safety concerns.

According to sources familiar with the situation, an independent certifier formally assessed October’s completed work, which should have triggered payment release. However, Webuild claimed Sydney Metro did not release those funds and has urged the government for immediate action so subcontractors and workers can be paid ahead of the holiday period.

Webuild has been self-funding construction amid the ongoing funding dispute, reportedly spending $120 million monthly since June while receiving only $65 million from the government.

Parklife’s additional funding request encompassed costs for elevated walkways required for fire access and egress — a change to the original design following disagreements with the firefighters’ union. NSW Transport Minister John Graham approved this variation but rejected other claims, including charges related to tunnel specifications and increased labor costs attributed to industrial relations issues linked to CFMEU demands.

“Since negotiations have ended, Metro has determined those claims in accordance with the contract,” Graham said. “Our expectation is that Parklife, including Webuild, will deliver the project as per the contract, targeting completion in September 2027.”

However, insiders on the site express skepticism about meeting the 2027 deadline, with some suggesting late 2028 may be more realistic given the current progress. Since May, Webuild has intermittently slowed work by reducing night and weekend shifts and cutting overtime in response to the funding impasse. Following the breakdown in negotiations, daytime shifts have also been scaled back.

With the NSW state election scheduled for March, the dispute appears unlikely to be resolved before that time, casting uncertainty over the future timeline of the Western Sydney Airport metro project.